Projects

Deepwater Expedition Shipyard Upgrade Project

Upgrade of Topside and Safety Critical Systems on location in Singapore before the vessel’s campaign in Saudi Arabia.

Paktim Energy Ltd were contracted to survey the existing PA/GA system, survey for a new CCTV system and complete a comprehensive EX Inspection.

Paktim Energy Project Managed all E&I Project under Paktim Energy remit, making recommendations regarding the existing systems to bring them in line with regulations. All Stakeholders agreed that Paktim Energy should complete all recommendations and Upgrades.

    Paktim Energy
  • Total Nº of Paktim Energy Personnel – 38
  • Project Manager – 1
  • Electrical Supervisors – 6
  • Electrical Technicians – 31

The Paktim Energy team successfully completed the following systems & work scopes:
PA/GA system – New racks and a complete system rewire, integration with ESD and F&G systems including commissioning.
Hernis CCTV System – A new CCTV system comprising of 36 cameras and control station were installed, tested and commissioned.
Hazardous Area Equipment Register – Compiled full Hazardous Area Register of Electrical equipment, carried out initial detailed inspections of new installations, and rectified outstanding punch list items.